If it takes 42 minutes to load 3\frac12 trucks, how

tebollahb

tebollahb

Answered question

2021-12-26

If it takes 42 minutes to load 312 trucks, how many minutes will it take to load 612 trucks?

Answer & Explanation

karton

karton

Expert2022-01-08Added 613 answers

We know that it takes 42m to load 312 trucks.
We want to find out how long it takes to load 612 trucks.
Too bad it was not the time wanted to load 7 trucks, because:
7 trucks =2(312) trucks so the answer would be:
2(42m)=84m for 7 trucks.
The reason we should bother with this answer is because:
Now we have an estimate for the real answer we will need to find (must be slightly less than 84m).
We could find the time it takes to load 1 truck by dividing the time (42m) by 312 and 312=6+12=72
42m72=42×27=84m7=12m after invert and multiply.
Then we could multiply the time to load 1 truck by 612 as asked:
12m×612=72m+12(12m)=72m+6m=78m
And that is in line with our estimate of 84m calculated previously.

user_27qwe

user_27qwe

Skilled2022-01-08Added 375 answers

Explanation:
The more trucks, the more minutes.
42x=3.56.5x=426535=613

nick1337

nick1337

Expert2022-01-08Added 777 answers

Given that 42 minutes are required to load 312 trucks.
Let ‘x minutes’ be the time to load 612 trucks.
312 trucks 42 minutes
612trucks x
By cross multiplication
312×x=612×42x=(612×42)/312=(132×42)72x=78
Thus x=78 minutes

Do you have a similar question?

Recalculate according to your conditions!

Ask your question.
Get an expert answer.

Let our experts help you. Answer in as fast as 15 minutes.

Didn't find what you were looking for?