Path A-B-E has a 55% probability of being completed within 3 weeks. Path C-D-F has a 90% probability of being completed within 3 weeks

arenceabigns

arenceabigns

Answered question

2021-09-07

Path A-B-E has a 55% probability of being completed within 3 weeks. Path C-D-F has a 90% probability of being completed within 3 weeks. If these are the only two paths in a project network, what is the probability the project will be completed in 3 weeks?

Answer & Explanation

unessodopunsep

unessodopunsep

Skilled2021-09-08Added 105 answers

Solution