Analysis of daily output of a factory during a 8-hour shift shows that the hourly number of units y produced after t hours of production is 
y=10t+12t2t3 
0t8 
1) After how many hours will the hourly number of units be maximized? 
2) What is the maximum hourly output?

Answer & Explanation

Ida Perry

Ida Perry

Beginner2021-11-18Added 20 answers

1) For maximize hourly unit y=0
y=10+t3t2=0
3t2t10=0
3t2+5t6t10=10
t(3t+5)2(3t+5)=0
t=2, 53 (Not posible)
The maximum number of units per hour will be reached after two hours
2)
For maximum hourly output
y)t=2)=10(2)+12(2)2(2)3
=2028
=14