Let T be the time needed to complete a job at a certain factory. By us

nemired9

nemired9

Answered question

2021-12-11

Let T be the time needed to complete a job at a certain factory. By using the historical data, we know that
P(Tt)={116t2for 0t41for t4
a. Find the probability that the job is completed in less than one hour, i.e., find P(T1).
b. Find the probability that the job needs more than 2 hours.
c. Find the probability that 1T3.

Answer & Explanation

Lynne Trussell

Lynne Trussell

Beginner2021-12-12Added 32 answers

Let T be the time needed to complete a job at a certain factory. 
P(Tt)={116t2for 0t41for t4  
 

(a) From the given information 
P(T1)=116(1)2=116 
P(T1)=0.0625 


(b) Let P(T2)=1P(T2) =1116(2)2=1116(4)=114=34 
P(T2)=0.75 


(c) P(1T3)=P(T3)P(T1) =116(3)2116(1)2=116(91)=116(8)=12 
P(1T3)=0.5

Do you have a similar question?

Recalculate according to your conditions!

New Questions in High school statistics

Ask your question.
Get an expert answer.

Let our experts help you. Answer in as fast as 15 minutes.

Didn't find what you were looking for?